Hydro-Generation / Water Conveyance
Back
Hexavalent Chromium Treatment System
Project
Performing local remediation
Syblon Reid was awarded a contract to perform well improvements at five sites. The primary scope of work revolved around installation of ion exchange treatment systems. Part of Syblon Reid’s responsibility was to coordinate with the supplier of the ion exchange treatment systems to ensure all accessory systems and existing equipment were properly integrated. Several critical tie-in’s for the new installations were performed during limited outage windows without delay. As a secondary scope of work, Syblon Reid performed miscellaneous control system upgrades. After installations were complete, we successfully performed pressure testing and chlorination.
Location
Sacramento County, CA
-
Market
Emergency Response
-
Services
Environmental Remediation
Gallery
Gallery
Facts & figures
Facts & Figures
7,290 +
crew labor hours