Working on, in, and around water
During a dive inspection of the three 6-foot diameter Low-Level Outlet (LLO) gates on Kerckhoff Dam, substantial leakage was discovered, along with extremely high corrosion. Syblon Reid was awarded the contract to rehabilitate the LLO’s. The scope of work included dredging the accumulated silt on the upstream side of the dam, demolishing and replacing the existing steel LLO components, and removing and replacing the existing LLO sluice gates, actuators, and pedestals.
Location
Kerckhoff Lake, Auberry, CA
-
Market
Hydro-Generation / Water Conveyance
-
Services
Heavy Civil Mechanical
Marine Work
Gallery
Gallery
Facts & figures
Facts & Figures
800 +
cubic yards of dredged material